Two weeks
on from my last update and I’m extremely happy to report that construction of
the layout is ploughing ahead. From my point of view, the progress made has
been nothing short of phenomenal, taking into account that apart from
verbalising what is in my mind and how I think it should be built, the actual
construction has been the sole effort of a mate of mine.
Making this
even more impressive (to me anyway), is that until this project started my mate
has had nothing to do with model trains at all, so building a reasonably large
double level semi modular layout as an introduction to the hobby is no small
feat.
For those
of us in the hobby, building a layout starts with a picture in our head of
exactly what we want, therefore from the beginning we have a fair idea of what
we are working towards and a pretty good idea of how we will do it. Trying to
explain in enough detail to somebody else exactly what is in your mind, so that
they can visualise the finished result and then construct it, is not as easy as
it may sound, and again I can’t thank my mate enough for the effort involved in
the mental translation of my thoughts and ideas into an actual physical,
practical and functional layout.
As for the
actual progress, as the layout sits at the moment, all of the individual module
assemblies that make up the lower and upper levels have been completed, the
back scene boards have been completed around the entire layout on both levels, and the boards that are essentially the sky have also been completed for both levels.
Like a lot
of things the photos probably don’t do justice to the amount of work involved
in getting to this point, but I would estimate that from bolting the steel
brackets to the bench top, to where the layout currently is, has taken six, ten
to twelve hour days, so sixty to seventy hours in total. If you put that into
typical “hobby time” terms, where you might spend an hour a day every day, or
maybe four to six hours over the weekend, this would represent around ten to
twelve weeks of work.
At the end
of the final day’s work, we temporarily attached a piece of timber with two
five meter strips of LED lights, one warm white strip and one variable RGB
strip, illuminating a section of the bottom deck, just to get an idea on
brightness, and how the variable colour RGB strip could be adjusted to give an
acceptable hue, as getting a fair representation of natural sunlight is always
a challenge with conventional lighting.
Without any
actual scenery or trains in position I cannot say that I have found the correct
mixture of lighting, but after having a short fiddle with the RGB colour
palette, I am fairly confident that I will be able to find a setting that is
more than acceptable.
The reason
for choosing to use two separate LED strips, one being a variable RGB strip, is
that the ability is there if you really want to, to get a representation of a
sunrise or sunset hue which is typically slightly orange, or at the extreme, a
night time hue which is typically represented with a blue colour.
The next
phase of construction will probably centre around figuring out exactly how we
are going to mount the fascia panels that the LED light strips will be mounted
on, what mounting angle of the LED strips gives the best spread of lighting
across the modules, and determine where power supplies will need to be
positioned around the room to power the LED strips. Like most things there is a
considerable amount of time thinking about these decisions as opposed to
actually doing it, but the extra time taken in thinking these things through
thoroughly is well worth it if you can do it once and it works perfectly.
If I had to
make a few key points on the construction so far it would be the following.
The use of
the steel brackets that the layout modules, back scene boards, sky boards and
fascia boards will attach to, whilst being somewhat unconventional, are
extremely strong relative to their size, as there is no way timber brackets
made from only 25mm x 25mm sections would be strong enough to support what the
steel brackets do.
Building
the layout with each section as a modular assembly using the compressed foam
panels with a light timber frame, produces an incredibly strong and very light
assembly, that is very easy to lift into and out of position. This will also
make working on each module extremely easy, no working upside down under bench
work to do wiring, and being able to have the module in the centre of the room
when working on it gives access to all sides, which will make constructing
scenery that would normally be hard against the backboard very simple.
Modular
construction also means that if at any time a section of the layout might want
to be changed, it is a very simple process to remove and replaced with another
module with different track layout or scenery, and while this is not something
that would happen often, the option is there to do it very easily.
Another
option would be the ability to take various modules that form a section of the
layout to an exhibition, there are probably not too many permanent style home
layouts that you could do this with.
That’s
about it for now, but I hope to be able to report back in the not too distant
future with some more progress reports.
2 comments:
Modular is the way to go, you can pull out sections for service/ exhibitions, and at the end of your days you can transplant some to your layout to your nursing home. Forward thinking today is lacking in both in prototype and in model form. Think of your future when modelling the past.
Regards Glenn.
Darren, it is good to have real mates who will do this for you.
The layout is looking good!
Ray P
Post a Comment